What are the development plans for the Islands District?

What are the development plans for the Islands District?

Development works on other islands continue mainly to improve the living environment of existing residential districts. Reclamation, road and drainage works at the central and north-western parts of Peng Chau are near completion. Reclamation, road and drainage works at Yung Shue Wan on Lamma Island are also in progress. Construction of the north-eastern riverwall and site formation work adjacent to Lung Tin Estate in Tai O were substantially completed in July. Construction of a sheltered boat anchorage in Tai O is expected to start in early 2003 for completion in 2005. In Cheung Chau old town, detailed design of the Stage 2 improvement works to existing roads and drains is in progress. Construction is scheduled to commence in late 2003 for completion in late 2005.

 